Calendrier

Schedule

 

<
February 24, 2006
completion of FMC right
January 7, 2006
completion of FMC left
December 2, 2005
complete achievements of the parts for the right FMC
November 23, 2005
assembly glareshield ( protection counters the entrees dust )
November 16, 2005
Realization door cabin
November 2, 2005
control of the Io-card cards
October 20, 2005
test MIP inputs
October 14, 2005
programming of all the possible functions for the pedestal
October 10, 2005
update Magenta program with test synoptic on screen ECAM
October 2, 2005
Test with FS9 of the whole of the segment display and coders for frequencies COM and TRANSP
August 24, 2005
modification wiring of coders MCP for management leaves the phaser decoder
August 8, 2005
Cablages elements of MIP and his connection card
July 17, 2005
Installation of a screen for secondary EICAS inferieur and add computer for mannagement ECAM
pour gestion des fonction ECAM
July 7, 2005
Realization of the lighting of the MIP panels
June 20, 2005
test addressings of pedestal
June 8, 2005
Watches realization and compass of central amount
May 5, 2005
ceiling lights installation of cabin with variator of intensity
May 2, 2005
connection pedestal to interfaces
March 6, 2005
test screen FMC
March 1, 2005
Completion of the Wiring of pedestal
february 18, 2005
precablage of the trush leveller
february 14, 2005
Realization of the laterales glass of cabin
January 10, 2005
First CDU cabling
December 20, 2004
Installing the IO-Cards
September 30, 2004
Cockpit top adaptation
August 2, 2004
Interfaces box building
July 28, 2004
Project Magenta installation
July 6, 2004
Project Magenta 2 clients PC installation
June 15, 2004
MCP, EFIS and ECAM cabling termination
June 10, 2004
Photon cards réceipt
April 3, 2004
Circuit-breaker panel building
March 20, 2004
Panel cabling
March 14, 2004
Overhead cabling
March 1, 2004
MCP cabling starts
February 23, 2004
Electronics spare parts ordering
February 12, 2004
Screens installing
February 5, 2004
Pedestal cabling
January 23, 2004
Panel and pedestal general structures are installed and painted, the FDS elements are adjusted to the boards edges. EFIS, EICAS and MCP and the "peak" are installed
January 16, 2004
Full inventory of buttons, interfaces and others parts, small electronics spare parts orders
January 12, 2004
Borders for the screens, installation of a plexiglass
January 8, 2004
Buying two car seats and fixing them on slides
December 23 2003
Thrust leveller support installation , and ajusting it in the pedestal
December 16, 2003
1st try to ajust the packs on the basis, the space required becomes more precise
December 12, 2003
1st temporary installation of the panel elements, and adjusting of the more sophisticated pieces is finished
November 25, 2003
First spare parts are received from FDS
November 11, 2003
A basic prototype is realised to define precise basis measurements
November 9, 2003
End of the work, the room is ready to receive the cockpit
October 23, 2003
Order of the FlightDeck Solutions boards
September 10, 2003
Building started
August 1, 2003
Building authorization is requested